The Vanashakti Review: Shaping the future of environmental clearances and compliance

Ananya Chaudhari
Mansi Govindswamy

Introduction

Law is rarely a straight line; legal history proves that even the highest court must sometimes weigh the strict letter of the law against its real-world impact. This delicate balance was put to the ultimate test in the recent review of the Vanashakti judgment.

On November 18, 2025, in CREDAI v. Vanashakti, the Court withdrew its earlier ruling that had categorically prohibited the grant of environmental clearances after construction had already commenced. This reversal underscores a significant doctrinal shift in balancing the “prior clearance” rule against the economic imperatives of a developing state. By a 2:1 majority, the court chose to protect the continuation of extensive infrastructure projects over strict procedural compliance. 

The root of the conflict

 

The dispute arose from a series of executive measures aimed at regularising projects that had violated mandatory environmental clearance requirements. 

 

2017 Notification – dated 14th March 2017 

  • Issued under the Environment (Protection) Act, 1986. 
  • Created a mechanism to grant post-facto Environmental Clearances ( EC’s) to projects that had already commenced construction, expanded production capacity, or changed their product mix without prior permission. 

 

When challenged in the Madras High Court, the Union Government gave a solemn undertaking that this was strictly a one-time measure. It provided a limited six-month window for applications, which was later marginally extended to April 2018. 

 

2021- Office Memorandum –  dated 7 July 2021 

  • The 2021 office Memorandum was issued pursuant to directions of the National Green Tribunal (NGT). The NGT had directed the Ministry of Environment, Forest and Climate Change to develop a structured Standard Operating Procedure (SOP) to address instances where projects had proceeded in violation of environmental clearance requirements. 
  • The Standard Operating Procedure introduced by the 2021 OM lacked both a specified timeframe and operational boundaries. By failing to include a clear expiration, it effectively created a ‘perpetual’ loophole, allowing developers to bypass prior environmental scrutiny and seek legalisation at any future date. This weakened the rule of law and prioritized economic convenience over ecological protection

 

The Original Vanashakti Judgement – May 16, 2025

 

The Hon’ble Court struck down the 2017 and 2021 office memoranda in a landmark ruling. 

  • Core finding: The Court held that the concept of ex-post facto environmental clearance is “completely alien” to Indian environmental jurisprudence and is “anathema” to the principles underlying environmental protection. 
  • Departing from earlier precedents (Common Cause, Alembic, Electrosteel), where the court acknowledged the law but permitted the ongoing projects, Vanashakti aligned the outcome with the legal reasoning. Even if penalties are paid, any project built without the mandatory prior clearance faces immediate suspension and potential demolition to uphold the sanctity of environmental regulations. 
  • To prevent widespread disruption, the Court stated that environmental clearances already granted under the 2017 and 2021 rules would remain effective, but no new clearances would be issued under these frameworks.

 

The Reversal : CREDAI v Vanashakti – November 18, 2025

 

Majority Observations: 

  • The Supreme Court reviewed the Vanashakti judgement on a petition for recall.

Vanashakti had ruled that projects  under construction must be stopped or demolished, even after payment of penalties, and operations already commenced must cease.

  • Former CJI noticed that this contradicted the 2021 OM and 2017 Notification, which permits EC’s only for legally permissible projects and mandates demolition only where projects are impermissible or environmentally unsustainable. 
  • The survival of critical public infrastructure worth over Rs.20,000 crore now hangs in the balance. Major projects such as AIIMS Odisha, the Vijayanagar Greenfield Airport, and several Common Effluent Treatment Plants (CETPs), could face demolition despite having undergone rigorous environmental assessments. Such an action would not only drain the public finances but also create a secondary environmental hazard due to the massive volumes of debris it would generate. 
  • It would further result in enquity as the earlier EC’s remains protected.  
  • The 2017 notification and the 2021 OM were not regressive measures but reflected ground realities, balancing enforcement with practicality 
  • The court rejected the ‘demolish-first’ approach, noting it would trigger:

1.Severe financial strain and loss of public/private revenue 

  1. Production of debris which did not serve a useful purpose.
  2. Waste of resources and causing undue hardship
  • The state retains the power to relax regulatory rigor in certain cases; a rigid ‘demolition first’ approach is impractical, environmentally harmful, and contrary to public interest. 
  • Section 15 of the Environment (Protection) Act deals only with the penalties and does not mandate demolition or prohibit regularisation. 

 

Unfavourable and Favourable Aspects of  the judgement

The review judgement presents a complex mix of outcomes, both favourable and unfavourable, for environmental governance in India.

  • On the unfavourable side, the ruling undermines the EIA (Environmental Impact Assessment) four staged process, which requires terms of reference, detailed assessments, and public consultations before projects begin. Allowing these actions to take place after the project is underway turns the process into mere damage control, essentially enabling non-compliance in exchange for penalties. This can result in financial setbacks, repeated inspections, work stoppages, legal costs, and waste from demolishing or altering unauthorised structures, placing undue strain on stakeholders.
  • The judgement also opens doors for private actors, not just government projects, to seek similar retrospective approvals, further weakening compliance incentives. While citing projects like AIIMS, Vijayanagar Airport, and SAIL, it fails to restrict relief to critical public infrastructure and avoids addressing Article 21 directly, leaving the scope of environmental rights ambiguous. 
  • At the same time, favourable aspects, though limited, include recognition of the economic and operational challenges faced by certain critical projects if immediate demolition was mandated. The judgment highlights the challenges critical projects would face if demolished immediately, reflecting judicial sensitivity to societal impacts and a careful balance between development and environmental duties.

Critical review of the judgement 

 

  • The dissent strongly indicts the review judgment, characterizing it as a retreat from the Court’s established environmental commitments.
  • The dissent rejects the idea that protecting the environment impedes development, emphasizing that the Constitution upholds sustainable development and that economic growth and environmental conservation are complementary rather than conflicting objectives. 
  • It also criticises the view that demolishing illegal structures would increase pollution, observing that such reasoning is environmentally flawed and economically irrational, as it incentivizes illegal construction while penalising lawful compliance.
  • Further, the dissent highlights a troubling shift in the doctrinal emphasis: by prioritizing the polluter pays principle over the precautionary principle, the review judgement reverses settled environmental norms, treating compensation after damage as a substitute for prevention. 
  • It emphasizes that allowing relief to parties flouting statutory duties threatens to institutionalise environmental law violations and undermine the rule of law.

 

Conclusion

 

The Vanashakti review represents a watershed moment where the Supreme Court chose to trade procedural rigidity for economic pragmatism. By “setting the clock back” to shield Rs.20,000 crore of public infrastructure from the wrecking ball, the Court has signalled that “Sustainable Development” must account for the carbon and the capital already sunk into the existing projects. However, the true test for 2026 legal term will be ensuring this this retrospective fix does not become a permanent invitation for developers to bypass environmental scrutiny.

References

Confederation of Real Estate Developers of India (CREDAI) v. Vanashakti, 2025 SCC OnLine SC 2474 (India).

Mumbai

Pune

Bangalore

Singapore

Delhi

Compliance Management

Risk Management

Legal Solution

IPR

Corporate Governance

Consulting

Learn More

Connect with us

Contacts

Risk Management

Legal Solution

IPR

Corporate Governance

Consulting

Learn More

Connect with us

Contacts

© Copyright 2024, Legasis. All rights reserved.